$15.7 millionon record, all years (grant values can span several years)
$28.79per person in the province
242 yearsof work at the median full-time wage
| Source | Records | Value |
|---|---|---|
| Federal contract | 224 | $14.8 million |
| Provincial contract award | 7 | $844,620 |
| Public body | Level | Records | Value |
|---|---|---|---|
| Public Services and Procurement Canada | Federal | 224 | $14.8 million |
| Newfoundland and Labrador Hydro | Provincial | 6 | $776,930 |
| Nalcor Energy | Provincial | 1 | $67,690 |
| Year | Value | |
|---|---|---|
| 2016 | $946,821 | |
| 2017 | $752,586 | |
| 2020 | $42,494 | |
| 2021 | $1.8 million | |
| 2022 | $5.5 million | |
| 2023 | $3 million | |
| 2024 | $2.8 million | |
| 2025 | $545,372 | |
| 2026 | $351,801 |
Patterns
Awarded without competition
9Contracts given to one supplier without an open call for bids.
Same supplier, sole-sourced again and again
4A public body gave the same supplier three or more sole-source awards.
Priced just under a limit
3Amounts within 5% below an open-call limit.
Contracts that grew well past their award
1Federal contracts whose final value is at least double the original, and at least $25,000 more.
A flag is a question, not a finding.
Largest records
- Engineering Consultants - Construction $946,820.77
- Engineering consultants - Other $752,586.10
- Engineering Consultants - Construction $745,482.48
- Other professional services not elsewhere specified $459,181.71
- Engineering consultants - Construction $447,571.53Flagged: Contracts that grew well past their award
- Other professional services not elsewhere specified $403,364.80
- Other professional services not elsewhere specified $304,828.20
- O-Professional Services not Elsewhere Specified $266,067.45
- Other professional services not elsewhere specified $256,225.06
- Engineering consultants - Construction $255,098.50
- Other professional services not elsewhere specified $236,848
- Happy Valley Interconnection Project Extension due to COVID-19 $228,880Flagged: Awarded without competition; Same supplier, sole-sourced again and again
- MSO Bay D’Espoir Transformer Refurbishments $223,016.23
- Other professional services not elsewhere specified $214,376.10
- Other professional services not elsewhere specified $174,560.66
- Other professional services not elsewhere specified $163,067.91
- Other professional services not elsewhere specified $140,452.49
- Other professional services not elsewhere specified $130,720.41
- Other professional services not elsewhere specified $130,353.65
- O-Professional Services not Elsewhere Specified $130,078.80
- Muskrat Falls - Happy Valley Interconnection Project Extension due to COVID-19 $129,000Flagged: Awarded without competition; Same supplier, sole-sourced again and again
- O-Professional Services not Elsewhere Specified $121,487.15
- Other professional services not elsewhere specified $120,020.25
- Other professional services not elsewhere specified $118,851.35
- Other professional services not elsewhere specified $116,360.25
- Svc Rltd to Remediation of Contaminate Sites $116,206.93
- Other professional services not elsewhere specified $114,953.16
- Other professional services not elsewhere specified $112,366.07
- Other professional services not elsewhere specified $111,931.02
- Study on Menihek Firm Load and Excess Energy $111,867Flagged: Awarded without competition; Same supplier, sole-sourced again and again
- O-Professional Services not Elsewhere Specified $105,000Flagged: Awarded without competition
- Other professional services not elsewhere specified $104,514.30
- Other professional services not elsewhere specified $103,297.60
- Other professional services not elsewhere specified $103,081.97
- Other professional services not elsewhere specified $99,650.90
- Other professional services not elsewhere specified $97,367.08
- O-Professional Services not Elsewhere Specified $94,860.05
- O-Professional Services not Elsewhere Specified $94,528.85
- O-Professional Services not Elsewhere Specified $89,965.65
- Other professional services not elsewhere specified $89,352.82